Ashfurlong Road – Sheffield – New Residential House

Trueline Steel Structures Ltd alongside a valued client have successfully constructed a new stick and beam steel framed house comprising of 46 Tonnes of Hot rolled steel with intricate connections throughout.

Due to the evolving scope our drawing office worked closely with the design team, tweaking the drawings until the team was completely satisfied.

Installation was onerous due to there only been one possible crane position, and deliveries having to be off-loaded from the road. On top of this access was hindered further due to the basement, accordingly the correct MEWPs were selected and put in their starting position using the crane.